We use Lighthouse as a scrum tool. Milestones are sprints, tickets are user stories. Tickets that are not assigned to a milestone form the product backlog. It works pretty good, but we miss some things:

Story points:
We assigned points to the tickets that we want to put in a separate field, now we misuse the tags but it is hard to do metrics that way

Burnup chart:
We would like to see a (line) chart that shows a line with the total amount of story points currently entered for the whole project and a line that shows the total amount of story points of tickets that are resolved (a marker per milestone). The lines should end up touching each other.

  1. 1 Posted by Nicole on 09 Jan, 2013 03:41 PM

    Nicole's Avatar

    Thanks for the feedback! We're currently working on an implementation of points, but any additional information you could share about your use case would be appreciated. We'll update this discussion when we have something deployed to production.

    Thanks,
    Nicole

  2. Support Staff 2 Posted by Tiger Team on 09 Jan, 2013 06:16 PM

    Tiger Team's Avatar

    The good news is this is pretty much exactly how we're implementing it, so that's awesome.

  3. brandi closed this discussion on 24 Jan, 2013 09:57 PM.

Discussions are closed to public comments.
If you need help with Lighthouse please start a new discussion.

Keyboard shortcuts

Generic

? Show this help
ESC Blurs the current field

Comment Form

r Focus the comment reply box
^ + ↩ Submit the comment

You can use Command ⌘ instead of Control ^ on Mac